PM Surya Ghar Muft Bijli Yojana lets a household install rooftop solar with a central subsidy of up to ₹78,000 and aims to make the first 300 units of monthly consumption effectively free. The whole process, from application to subsidy, runs online through one national portal. People who know the steps finish it smoothly. People who do not often get stuck between the vendor and the electricity company.
This guide takes you through each stage in the order it happens. For subsidy slabs, system sizing and payback, see our companion article on PM Surya Ghar Yojana.
The process in one view
| Stage | Who acts | What happens |
|---|---|---|
| 1. Registration | You | Create an account on the national portal |
| 2. Application | You | Submit rooftop solar application for your connection |
| 3. Feasibility | Discom | Technical clearance for the size you asked for |
| 4. Installation | Registered vendor | System is installed on your roof |
| 5. Net meter | You and discom | Apply for and install the net meter |
| 6. Commissioning | Discom | Inspection and commissioning certificate |
| 7. Subsidy | You and the ministry | Submit bank details; subsidy credited |
Discom means your electricity distribution company, the one that sends your bill.
Before you start
Keep these ready:
- Latest electricity bill, for the consumer number and sanctioned load
- Aadhaar and a mobile number
- Email address, if you have one
- A bank account in the name of the electricity consumer, with a cancelled cheque or passbook copy
- A clear photograph of your roof and an idea of the shade-free area
The applicant should be the person in whose name the electricity connection stands. If the connection is in a deceased relative’s name, get it transferred first. This is the most common cause of trouble at the subsidy stage.
Step 1: register on the portal
- Open pmsuryaghar.gov.in. A mobile app with the same name is also available.
- Choose the consumer option and then register.
- Select your state, district and discom.
- Enter your electricity consumer account number exactly as on the bill.
- Enter your mobile number and verify it with the OTP. Add your email if asked.
Step 2: log in and apply
- Log in with your mobile number and OTP.
- Open the rooftop solar application form.
- Check the connection details that appear, and fill in your address and the capacity you want to install.
- Upload a copy of the electricity bill.
- Submit the application and note the application number.
If you are unsure about capacity, use the calculator on the portal or the one on this site. As a rule of thumb, each kW generates about 120 units a month.
Loading calculator. If nothing appears, turn on JavaScript in your browser.
Step 3: feasibility approval
The discom checks whether the local network and your sanctioned load can take the system. The rules have been eased over time so that small home systems get clearance quickly, and in many areas approval for systems up to 10 kW is treated as granted automatically. You will see the status change on the portal and get an SMS.
If the size you want is more than your sanctioned load, you may be asked to apply for a load enhancement first.
Step 4: choose a vendor
Only installations by vendors registered with your discom on the national portal qualify for subsidy.
- On the portal, open the list of registered vendors for your district.
- Call two or three of them. Ask each for a site visit and a written quote.
- Compare the following, not just the price:
| Item | What to look for |
|---|---|
| Panel brand and wattage | Domestic content compliant panels; recent manufacturing date |
| Inverter | Brand, capacity matching the panels, warranty of at least five years |
| Structure | Hot-dip galvanised, with adequate height and wind rating for your area |
| Wiring and safety | Earthing, lightning arrester, DC and AC protection boxes |
| Service | Free maintenance period, response time, contact person |
| Payment terms | Advance amount, balance on commissioning |
- Select the vendor on the portal and sign a simple agreement. The portal provides a model agreement.
Never pay the full amount in advance. A common arrangement is a part payment at order, a part at delivery and the rest after commissioning.
Step 5: installation
A home system is usually fitted in one to three days once material arrives. Be present. Check that the panels are placed facing south or as close to it as the roof allows, that nothing shades them between about 9 am and 4 pm, and that the serial numbers on panels and inverter match the invoice.
After installation, the vendor uploads the plant details and photographs on the portal.
Step 6: net meter
- Apply for the net meter through the portal or the discom, as your state requires.
- Pay the net meter charges and testing fee to the discom, if applicable.
- The discom replaces your existing meter with a bidirectional one.
Net meter availability has been a bottleneck in some places. Raise it early with the vendor, who normally follows up on your behalf.
Step 7: inspection and commissioning
The discom inspects the installation, or accepts the documents uploaded, and then issues a commissioning certificate on the portal. This certificate is the key document for the subsidy. Download it and keep a copy.
Step 8: claim the subsidy
- Log in to the portal after the commissioning certificate appears.
- Enter your bank account number and IFSC.
- Upload a cancelled cheque or the first page of the passbook. The account holder’s name should match the electricity consumer’s name.
- Submit the subsidy request.
The central subsidy is transferred directly to the account, generally within about 30 days. State subsidy, where it exists, follows the state’s own timeline.
Taking a loan
If you need finance, click the loan option on the portal after applying. It takes you to the Jan Samarth platform, where you choose a bank and submit the application online. Loans for systems up to 3 kW are collateral-free and carry concessional interest. Sanction is quicker if your account with that bank is already active and your credit record is clean.
| Point | Typical terms for up to 3 kW |
|---|---|
| Loan amount | Up to about ₹2 lakh |
| Margin money | Around 10% of project cost |
| Interest | Concessional, linked to the repo rate |
| Tenure | Up to 10 years |
| Collateral | None |
Confirm the exact terms with the bank you choose.
Tracking your application
Log in at any time to see the stage: applied, feasibility approved, vendor selected, installation done, inspection done, commissioned, subsidy requested, subsidy released. Each change also triggers an SMS.
Where applications get stuck
| Stuck at | Reason | Fix |
|---|---|---|
| Registration | Consumer number not recognised | Type it exactly as on the bill; check the correct discom is chosen |
| Feasibility | Load or transformer capacity issue | Apply for load enhancement or reduce system size |
| Installation details | Vendor has not uploaded data | Remind the vendor; withhold final payment until done |
| Net meter | Meter not in stock | Escalate to the discom sub-division office |
| Subsidy | Bank name mismatch or account not seeded | Use the consumer’s own account; correct the name |
For unresolved issues, use the grievance option on the portal or call 15555.
After commissioning
- Clean the panels with plain water every two weeks, more often in dusty months.
- Check the inverter display or app weekly to see daily generation.
- Compare the import and export readings on your bill.
- Keep invoices, warranty cards and the commissioning certificate in one file.
Frequently asked questions
Can I install first and apply later?
No. Apply on the portal first. Systems installed outside the process do not get the subsidy.
Can I use an unregistered local electrician to save money?
Not if you want the subsidy. The installer must be a registered vendor.
How long does the whole process take?
With a responsive vendor and discom, six to twelve weeks from application to subsidy is common.
Is the portal free to use?
Yes. There is no application fee on the national portal.
Will my bill become zero?
It depends on your use and system size. Fixed charges on the bill usually remain payable.
Use only pmsuryaghar.gov.in and its official app. Websites that collect a “registration fee” for the scheme are not genuine.